While Foley Contracting has both completed and is currently undertaking Sea Wall reconstruction the most recent major project was the Eastern Breakwater Wall in Coffs Harbour NSW. The company moved over 40 000 tonnes of rock, placed 2500 handbars weighing between 16 and 28 tonne. A further 45 000 tonne of concrete was also used. The project took approximately 14 months to complete which was 5 months ahead of schedule.